Thursday, July 30, 2009

Site Works - 30 July


The day started with a visit from Structural engineer Peter Brunner. He clarified the requirements for the pads and re-bar, and inspected the bearing conditions at the pad locations.
We then used a water level to get a consistant level around the four pads.
And we kept digging to level off. One all holes were ready we were able to start fitting the formwork boxes to cast the pads in tomorrow.
Hardcore arrived on time which meant that we will be able to pour the foundations tomorrow.

No comments:

Post a Comment