Thursday, July 30, 2009
Site Works - 28 July
Our First day on Site!
The site was set out, and after prolonged, occasionally heated, but always intelligent discussion a final location was fixed, at an angle to the field, and holding the edge of the route down to the site.The centre of the site is to be marked with a central steel pole. This pole allows us to coordinate all set outs on site throughout the job as radii to this central point.
Ryan Kennihan dug the hole for the post, which was raised, plumbed and cast in concrete.
Once the concrete had set we could set out the site and commence digging the pads.
There are 4 pads, one at each corner of the dome. These are 900 x 900 x 300 concrete over 200 compacted hardcore. These pads are connected by tie bars which act to counteract the lateral forces from the dome.
Subscribe to:
Post Comments (Atom)
I was essentially imagine about it and you gave me the right information I really bookmark it, for further scrutinizing. Nevertheless, you ought to give more bits of knowledge about it.
ReplyDeleteDiscount Furniture
Awesome post share I say thanks to share this impressive post.Keep it. Solid color dress shirts MEN'S CLOTHING & FASHION APPAREL SINCE 1877. Shop Bachrach.com - Men's Suits, Shirts, Ties, Coats, Pants, Blazers & Accessories Online.
ReplyDeleteWhat a pleasant YouTube video it is! Awesome, I loved it, and I am sharing this YouTube record with all my colleagues.
ReplyDeleteMasonry San Diego
Actually writing computer programs is nothing anyway it's a rationale, on the off chance that you gain power on it a while later you are the expert else nothing.Masonry Contractors Solana beach
ReplyDelete