Tuesday, November 3, 2009

Site Works - latest photo

Friday, October 9, 2009

Site Works - Latest Images



Thursday, October 8, 2009

Now What Exhibition


All the different Now What groups will be exhibiting their work in Smithfiled over the coming weeks. All are invited to the exhibition which opens Friday 9th at 7:30pm

Friday, September 25, 2009

Site Works - 20th September

Many thanks to Mark Halpin for these images.

Sunday, September 6, 2009

Site Works Aug.31 - Sep.5


We now have completed all of the necessary brickwork to proceed with the dome!





We have placed an additional timber guide within the structure to aid in the correct positioning of the tiles for the dome. This guide represents the line of 1/2 of the dome (or 1/4 of a sphere) from springing point to oculus.



The dome tiles are cut to fit with the arches and laid out prior to plastering and placement.




The first layer of tiles is laid with a mix of pure gypsum plaster which is mixed in small batches immediately prior to laying as it hardens quickly in 1-2 minutes.



These tiles are laid in correct position by triangulating the line off of the timber guide. With practice the tile placement has become much quicker and cleaner.


The second layer of dome tiling is laid with concrete and set at a diagonal angle relative to the first tile layer. The dome gains strength through this process of lamination while breaking the joints.


Doming will proceed all week.

Sunday, August 30, 2009

Site Works Aug 22-26






Work has been progressing all week on the brickwork corner buttressing as this needs to be in place prior to completing the dome. Work has been slow due to the high number of specials where the brick meets the arches, but we are almost over the hump(s). The dome has arisen in each of the corners but will begin in earnest next week. Thank you to all who have been putting in the hard hours on the brickwork, especially - Carthage, David, Mark, Bruno, Alex, Ian, Elaine, Rae, and Suzy.

Tuesday, August 25, 2009

Site works - 20th and 21st August

We've completed the arches and have started work on the dome. The key thing for the coming week is to keep the brick rising walls ahead of the dome, as we cannpt complete the dome until the walls are in place.
We used the lower course of the arches as a test for getting the placement of the slips right for the dome - and so used casting plaster to allow us to perfect the mixing of small amounts of plaster (enough for one slip) to the correct consistancy quickly. This will be critical for the dome as we will be relying on the plaster to set quickly and to hold each slip in place as we work upward.